Changing a contract with Scodeller Construction, Inc. for overband crack fill to add $797,445.80, for a total of $2,695,986.80, and extend the end date from December 31, 2026 to June 30, 2027

Changing a contract with Scodeller Construction for overband crack fill to add $797,445.80

Official wording

Changing a contract with Scodeller Construction, Inc. for overband crack fill to add $797,445.80, for a total of $2,695,986.80, and extend the end date from December 31, 2026 to June 30, 2027

Weigh inWhere you stand, and why, goes to your representatives
None yetvotes on the record on this issue
9members of Detroit City Council decide thisWho decides
OpenNo vote date is set yetWeigh in now

Add your voice, your neighbors add theirs, and the count goes to the people who decide before they vote.

More on this issue

CityDetroit City CouncilPassed Apr 28

Who decides this

  • Mary WatersAt Large 1No vote on record
  • Coleman A. Young IIAt Large 2No vote on record
  • James TateDistrict 1No vote on record
  • Angela Whitfield-CallowayDistrict 2No vote on record
  • Scott BensonDistrict 3No vote on record
  • Latisha JohnsonDistrict 4No vote on record
  • Renata MillerDistrict 5No vote on record
  • Gabriela Santiago-RomeroDistrict 6No vote on record
  • Denzel Anton McCampbellDistrict 7No vote on record

Whole board: passed, Apr 28 (the record does not list each member's vote)

Decided, Apr 28: The council voted on the Contract No. 6006031-A1- 100% Major Street Funding – AMEND 1 – To Provide an Increase of Funds and an Extension of Time for Overband Crack Fill. – Contractor: Scodeller Construction, Inc. – Location: 51722 Grand River, Wixom, MI 48393 – Previous Contract Period: February 15, 2024 through December 31, 2026 – Amended Contract Period: February 15, 2024 through June 30, 2027 – Contract Increase Amount: $797,445.80 – Total Contract Amount: $2,695,986.80. PUBLIC WORKS. It passed.

Loading the votes.

Follow issues like this one

We will email you when there is news on the topics you pick: a vote, a hearing or a date when residents can speak.

What do you want to hear about?

We send you one email first to confirm your address. SourceLine never sells or shares your email address.

About these figures

Every figure on this page shows the year it describes. Public agencies release their numbers on their own schedules, often a year or more after the work of counting is done. The Census Bureau, for example, publishes its five year community survey each December, and the national reading test is given every two years. That is why some figures are not from this year. SourceLine updates each one as soon as the agency publishes it.

For some counties and small towns, SourceLine has not found meeting records online. Where it has not, we add them as they become available. A page that says SourceLine hasn’t updated a record yet means exactly that.