Ratifying revisions to three previously approved permanent easements for Georgia Power's Ashley Park to Creola 230 kV Transmission Line

Ratifying revisions to three previously approved permanent easements for Georgia Power's Ashley Park to Creola 230 kV Transmission Line

Weigh inWhere you stand, and why, goes to your representatives
1votes on the record on this issue
5members of Fayette County Board of Commissioners decide thisWho decides
OpenNo vote date is set yetWeigh in now
The latest recorded vote on this issue, January 8, 2026
Yes3
No2

Official record of Fayette County Board of Commissioners.

Add your voice, your neighbors add theirs, and the count goes to the people who decide before they vote.

More on this issue

CountyFayette County Board of CommissionersPassed Jan 8

Who decides this

  • Charles W. OddoCounty Commission 5 At LargeVoted noEmail
  • Eric K. MaxwellDistrict 1Voted yesEmail
  • Lee HearnDistrict 2Voted yesEmail
  • Edward G. Gibbons Jr.District 3Voted yesEmail
  • Charles D. RousseauDistrict 4Voted noEmail

Whole board: passed 3 to 2, Jan 8

Decided, Jan 8: The board voted 3 to 2 on the motion to approve ratification of revisions to three (3) previously approved permanent easements for Georgia Power's Ashley Park - Creola 230 kV Transmission Line. It passed.

Loading the votes.

Follow issues like this one

We will email you when there is news on the topics you pick: a vote, a hearing or a date when residents can speak.

What do you want to hear about?

We send you one email first to confirm your address. SourceLine never sells or shares your email address.

About these figures

Every figure on this page shows the year it describes. Public agencies release their numbers on their own schedules, often a year or more after the work of counting is done. The Census Bureau, for example, publishes its five year community survey each December, and the national reading test is given every two years. That is why some figures are not from this year. SourceLine updates each one as soon as the agency publishes it.

For some counties and small towns, SourceLine has not found meeting records online. Where it has not, we add them as they become available. A page that says SourceLine hasn’t updated a record yet means exactly that.